Papchan Bridge
Const. of 2X26 meter bridge at Papchan
Construction of Papchan Bridge Dist Bandipora

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Bridges
Districts Passing: BandiPora

Constituency Passing:

BandiPora
Status: Works Completed
ERA Ref: Transport/Srinagar/Road 17 Type:Works Mode: LCB
ERA Pac ID: 0030
PCSS No: 0062
Scope of Work: 2 x 26.285 Mts
Contract Cost in Rs crore: 2.8388
Dynamic Cost in Rs crore: 4.55
Contractor Details Sofi and Company
Date of Signing of Contract 04 December 2007
Date of Start of Work (NTP) 08 December 2007
Completion Period (15 Months)
Completion Date as per Contract 08 March 2009
 
Work completed on 31-05-2009
.Handed over to (R&B)PWD